Approve findings to authorize an exemption to the competitive bidding requirements and approve use of the alternative contracting method of Construction Manager/General Contractor for the Carolina Trunk Work Zones 01 & 03 Rehabilitation Project
View source document ↗- infrastructure utilities
- procurement
- Department
- Environmental Services
- Introduced by
- Former Commissioner Mingus Mapps
- Status
- Passed
▸ Full text (the legislation as adopted)
The City of Portland ordains: Section 1. The Council finds: The Bureau of Environmental Services (BES) has identified the existing Carolina Trunk crossing highway Interstate-5 (I-5) between SW Slavin and S Macadam in Southwest Portland to be in poor condition requiring immediate rehabilitation and replacement. BES has planned to separate the sanitary sewer and stormwater systems within the Carolina basin. This requires construction of new sewer and stormwater collection pipes including a new pipe crossing under I-5 that is parallel and is in addition to the existing trunk currently in use. The location, underground conditions and depth of the existing Carolina Trunk will require specialized skills in deep shaft excavation, trenchless large utility construction, work on private properties and in proximity to a major highway, complex sewer flow bypass coordination and traffic control, as well as experience in complex construction approaches, risk and safety control, construction sequencing, scheduling, and cost estimating to overcome the challenges and risk associated with this work. Procurement Services and BES recommend using the alternative contracting method of Construction Manager/General Contractor (CM/GC) for the Project. The Council is the Local Contract Review Board with the authority to exempt certain public contracts from the competitive bidding requirements of ORS Chapter 279C and Portland City Code 5.34. Draft findings addressing favoritism, competition, substantial cost savings, operations, budget and financial data, public benefits, value engineering, specialized expertise required, public safety, market conditions, technical complexity, and funding sources recommended by the City, substantially in the form attached hereto as Exhibit A (collectively, the “Findings”), were made available and a notice of the public hearing of this Ordinance was published fourteen (14) days in advance of this public hearing. The estimated CM\GC construction contract is approximately $20,000,000. Funds are available in the Sewer System Operating Fund, WBS Element E11004 with the Bureau of Environmental Services FY 2022-2026 Capital Improvement Plan (CIP). The Project Estimate Confidence Level Rating Index, per Binding City Policy BCP-ADM-1.13, is Low. NOW, THEREFORE, the Council directs: Council hereby approves the Findings, as attached as Exhibit A, and on that basis exempts the Carolina Trunk Work Zones 01 & 03 Rehabilitation Project from the competitive bidding requirements of ORS Chapter 279C. The Chief Procurement Officer is hereby authorized to use an alternative competitive solicitation process to select a CM/GC contractor for the Project and, upon selection of a CM/GC, is authorized to execute a contract for CM/GC pre-construction services during design phase of the Project, provided the contract has been approved as to form by the City Attorney. Upon the Council’s acceptance of the Chief Procurement Officer’s report recommending the acceptance of a Guaranteed Maximum Price from the CM/GC for the Project, the Chief Procurement Officer is authorized to negotiate and execute a contract for the construction of the Project, provided the contract has been approved as to form by the City Attorney’s office. The Mayor and City Auditor are hereby authorized to pay for the contract from the Sewer System Operating Fund Budget when demand is presented and approved by the proper authority. As required by ORS 279C.355 and PCC 5.34.820C, BES will prepare and deliver a post project evaluation to the Council on behalf of the Chief Procurement Officer, once the City accepts the Project as complete.
Tally
Roll call (5)
- yea
- Dan Ryan 2yea
- yea
- yea
- nay